Capital Improvement Projects

Current Projects

 

AD Hare Water Renovations

(Project Manager - B.K. Bonge)

The project involves the construction of approximately 15,506 LF of 6” water main, approximately 13,496 LF of 4” water main, 6,215 LF of 2” water main, 20 post hydrants, 19 fire hydrant assemblies, fittings and associated appurtenances.  It will consist of replacing the existing (smaller) water mains with a larger one.  In addition, new water meters and boxes will be installed.  These installations will occur withint the rights-of-way or a general utility easement along private roads.

The roads that are included in the project are: Broughton Hall Road, Bunkerhill Lane, Joey Lane, Morton Waring Lane, Old Village Drive, Quail Drive, Ranch Drive, Shoreside Court, Summerton Court, West Lake Shore Drive, Academy Lane, Windy Hill Lane, Almond Street, Ben’s Circle, Bryan Drive, Cooper Store Road, Crestwood Drive, Lucas Street, Starbright Lane, Stormwatch Lane, Val-Mar Drive, Walsh Drive, AD Hare Lane, Alle Place, Ayers Drive, Buttonwood Lane, Cain Drive, Dial Lane, Doc Lacy Lane, Dooley Lane, Fellowship Lane, Fox Squirrel Lane, Graceland Drive, Harriets Way, Jolewis Lane, Lakenglen Drive, Louise Lane, England Road, Maries Lane, McCall Alley, Morning Dove Lane, Parsonage Road, Peggy Lane, Private Lane, Pinopolis Road and Shelby Lane.

The project is currently under construction.  Traffic controls and some water service interruptions are to be expected.  However, BCWS will do our best to minimize water service interruptions and advanced notice will be given prior to any planned service outage.  In addition to our crews, you will see contractors retained by us in the area.  These contractors are MJL, Inc., and Eadies Construction, Inc.  The construction is expected to be completed by the end of September.

 

Pump Station Modifications (PS032, PS011&PS049, PS203)

(Project Manager - Chris Troutman)

The project will modify three existing pump stations, Pump Station (PS) 032, PS049, PS203.  PS049 will be eliminated by PS011.  The modifications will provide more reliable and efficient wastewater transmission.  In addition to our crews, you will see contractors retained by us in the project areas.  Anson Construction Company will be constructing new wet wells, piping, pumps & motors, controls & SCADA, standby electrical power, site work, paving, and fencing.

     PS032

     344 Camelot Drive
     Goose Creek, SC 29445

     Expected Project Schedule: Begin Construction April 7, 2014
                                                  End Construction Mid-September 2014

     Design Flow: 1,270 GPM

     Approximate Cost: $459,500.00

     PS011 & PS049

     PS011 (to be modified)                    PS049 (to be demolished)
     323 St. James Avenue                    125 Southwold Circle
     Goose Creek, SC 29445                 Goose Creek, SC 29445

     Expected Project Schedule: Begin Construction Mid-August 2014
                                                  End Construction Late January 2015

     Design Flow: 1,000 GPM

     Approximate Cost: $632,320.00
 

     PS203

     1238 North Main Street
     St. Stephen, SC 29479

     Expected Project Schedule: Begin Construction Late July 2014
                                                  End Construction Mid-January 2015

     Design Flow: 200 GPM

     Approximate Cost: $443,780.00

Last update: July 25, 2014